Major Mining Infrastructure Project

FabEng successfully delivered a comprehensive $5M fabrication and installation project for BHP's mining operations, including conveyor systems, structural steelwork, and processing equipment.

ISO Certified
NATA Accredited
25+ Years Experience

Project Overview

Project Overview

This major mining infrastructure project showcased FabEng’s capability to deliver large-scale, complex fabrication and installation services in challenging remote environments. Working with BHP Billiton, we delivered a comprehensive solution that enhanced operational efficiency while maintaining the highest safety standards.

Project Scope

Fabrication Components

  • 2,500 tonnes of structural and process steelwork
  • Custom conveyor components and support structures
  • Processing equipment modifications
  • Maintenance access platforms and walkways

Installation Services

  • 3.2km of new conveyor system installation
  • Integration with existing operational systems
  • Commissioning and testing of all equipment
  • Training for operational and maintenance teams

Key Challenges Overcome

Remote Location Logistics The Pilbara location presented significant logistical challenges. We developed a modular fabrication approach that allowed for efficient transportation and on-site assembly.

Environmental Conditions The harsh mining environment required specialized materials and coatings. Our team selected appropriate protection systems to ensure long-term durability.

Operational Integration Working within an active mining operation required careful coordination and planning to minimize disruption to ongoing production.

Project Results

The project was completed successfully, demonstrating FabEng’s ability to deliver complex mining infrastructure solutions. Key outcomes included:

  • Safety Excellence: Zero incidents across 52,000+ work hours
  • Schedule Performance: Completed 2 weeks ahead of the original timeline
  • Cost Efficiency: 15% savings achieved through value engineering
  • Ongoing Partnership: Secured maintenance contract based on project success

This project has led to additional opportunities with BHP and reinforced our reputation as a trusted partner for major mining infrastructure projects across Australia.

Project Details

Client: BHP Billiton
Industry: mining
Location: Pilbara, Western Australia
Duration: 18 months
Project Value: $5.2 million
Status: Completed
2,500t
Steel Fabricated
Heavy-duty structural and process steel
3.2km
Conveyor Length
New conveyor system installed
52,000
Work Hours
Total project hours with zero harm

Project Challenges

  • Remote location with limited infrastructure access
  • Extreme environmental conditions and dust exposure
  • Tight project timeline with weather dependencies
  • Integration with existing operational systems

Our Solutions

  • Modular fabrication approach for easier transportation
  • Specialized coatings for harsh environment protection
  • Detailed project planning and risk management
  • Close collaboration with BHP engineering teams

Project Results

  • Project completed 2 weeks ahead of schedule
  • Zero safety incidents across 50,000+ work hours
  • 15% cost savings through value engineering
  • Ongoing maintenance contract secured
"FabEng delivered exceptional results on this complex mining project. Their attention to safety, quality, and schedule was outstanding."
Sarah Johnson
Project Manager
BHP Billiton

Project Gallery

Major Mining Infrastructure Project - Image 1
Major Mining Infrastructure Project - Image 2